Remove /generate-app: app shell is now milestone 01 of the plan

The initial app is no longer generated by a separate command. /plan-milestones
now always makes milestone 01 'App Shell Generation' (target platform asked in
the single question round): theme from design tokens, one screen per blueprint
entry, routes, reusable components — no feature logic — plus Playwright setup
and the e2e/app-shell.spec.ts smoke spec. It is executed like any other
milestone via /execute-milestones (which follows platform-ui-generation for it)
or /add-feature. Milestone 02 becomes the MVP core. All workflow diagrams,
skills, docs READMEs, AGENTS.md, and README updated; docs/design README also
gains the screen-inventory.md entry.

Co-Authored-By: Claude Fable 5 <noreply@anthropic.com>
This commit is contained in:
2026-07-02 14:10:07 +02:00
parent a4f80e8c8c
commit 1649a71781
13 changed files with 89 additions and 238 deletions

View File

@ -18,13 +18,14 @@ Roadmap (roadmap.md)
## Core Principles
1. **MVP first**: Phase 1 delivers the MVP; milestone 1 is its core — the smallest coherent, end-to-end usable product. Not a layer (e.g. "all the models"), but a vertical slice a user could actually use.
2. **Vertical slices**: Each feature cuts through UI → logic → data. Avoid horizontal milestones like "backend milestone" / "frontend milestone".
3. **One feature = one `/add-feature` run**: If a feature needs more than one steering directory to implement, split it. If it is a one-line change, merge it into a neighbor.
4. **One phase file = one `/execute-milestones` run**: A phase groups 13 milestones that together form a meaningful release.
5. **Dependency order**: A feature never lands in an earlier milestone than something it depends on, and a milestone never lands in an earlier phase than its dependencies.
6. **Exactly-once assignment**: Every feature belongs to exactly one milestone; every milestone to exactly one phase file. Deliberately deferred items go to the roadmap's "Later / Icebox" — nothing silently disappears.
7. **Living documents**: Phase files track status. `/add-feature` and `/execute-milestones` check off features (`[ ]``[x]`) as they complete, and milestone/phase statuses are updated in both the phase file and `roadmap.md`.
1. **App shell first**: Milestone 01 is always **App Shell Generation** — there is no separate generate-app command; the initial app is built as the first milestone (see "Milestone 01" below).
2. **MVP first**: Phase 1 delivers the MVP; milestone 02 is its core — the smallest coherent, end-to-end usable product on top of the shell. Not a layer (e.g. "all the models"), but a vertical slice a user could actually use.
3. **Vertical slices**: Each feature cuts through UI → logic → data. Avoid horizontal milestones like "backend milestone" / "frontend milestone".
4. **One feature = one `/add-feature` run**: If a feature needs more than one steering directory to implement, split it. If it is a one-line change, merge it into a neighbor.
5. **One phase file = one `/execute-milestones` run**: A phase groups 13 milestones that together form a meaningful release.
6. **Dependency order**: A feature never lands in an earlier milestone than something it depends on, and a milestone never lands in an earlier phase than its dependencies.
7. **Exactly-once assignment**: Every feature belongs to exactly one milestone; every milestone to exactly one phase file. Deliberately deferred items go to the roadmap's "Later / Icebox" — nothing silently disappears.
8. **Living documents**: Phase files track status. `/add-feature` and `/execute-milestones` check off features (`[ ]``[x]`) as they complete, and milestone/phase statuses are updated in both the phase file and `roadmap.md`.
## Inputs
@ -50,6 +51,20 @@ File naming: `phase[N]-milestones.md` with `N` starting at 1 (e.g. `phase1-miles
Use the structure in `template.md` for each phase file and for the roadmap.
## Milestone 01: App Shell Generation (always the first milestone)
The initial app is not created by a separate command — it is **milestone 01**, the first milestone of phase 1, executed like any other milestone (via `/execute-milestones phase1-milestones.md` or feature by feature with `/add-feature`). Implementation follows the **platform-ui-generation** skill for the design→code mapping.
Record the **target platform** (`web` | `flutter` | `winui3`) in the milestone's Scope. Its features are:
- [ ] Generate the app shell and theme from the design tokens — entry point, layout shell, and the platform's styling system converted from `design-tokens.json`
- [ ] Generate routes, screens, and reusable components from the UI blueprint — one screen per `ui-blueprint.json` entry, navigation wired, shared components extracted, **no feature logic**
- [ ] Set up Playwright and the app-shell smoke spec — `playwright.config.ts`, `test:e2e` script, and `e2e/app-shell.spec.ts` verifying the shell renders and every blueprint route navigates (see the e2e-testing skill; platform equivalents for flutter/winui3)
Definition of done (in addition to the standard one): the app runs, every blueprint screen is reachable, tokens are the only styling source (no hard-coded values), and no feature logic exists beyond what the documents describe.
**Dependency**: milestone 01 requires the design spec (`docs/design/`). Every later milestone depends on milestone 01.
## How to Slice Features
A well-sized feature:
@ -66,10 +81,11 @@ Too small (merge it): "Change button color" → fold into the feature that owns
## How to Group Milestones and Phases
1. Tag every feature with its PRD priority and its dependencies.
2. Milestone 1 (MVP core): the minimal dependency-closed set of P0 features that forms a usable product walk-through (a user can start, do the core job, and finish).
3. Following milestones: group remaining features by theme and priority, keeping each milestone a meaningful step on its own ("after milestone N, the user can additionally …"). Prefer 38 features per milestone.
4. **Phase 1** contains milestone 1 plus any milestone required to make the MVP releasable. **Following phases** group the remaining milestones into meaningful releases — prefer 23 phases with 13 milestones each.
5. A phase should be independently valuable: after `/execute-milestones phase[N]-milestones.md` finishes, the product is in a releasable state.
2. Milestone 01 (App Shell): always first — see "Milestone 01" above.
3. Milestone 02 (MVP core): the minimal dependency-closed set of P0 features that forms a usable product walk-through (a user can start, do the core job, and finish).
4. Following milestones: group remaining features by theme and priority, keeping each milestone a meaningful step on its own ("after milestone N, the user can additionally …"). Prefer 38 features per milestone.
5. **Phase 1** contains milestones 01 and 02 plus any milestone required to make the MVP releasable. **Following phases** group the remaining milestones into meaningful releases — prefer 23 phases with 13 milestones each.
6. A phase should be independently valuable: after `/execute-milestones phase[N]-milestones.md` finishes, the product is in a releasable state.
## Status Tracking Rules
@ -83,6 +99,7 @@ Too small (merge it): "Change button color" → fold into the feature that owns
Before finishing:
- [ ] Milestone 01 is the App Shell milestone, with its target platform recorded and the three shell features listed.
- [ ] Every P0/P1 PRD requirement maps to a feature in some milestone (or is explicitly in the icebox).
- [ ] Every feature appears in exactly one milestone; every milestone in exactly one phase file.
- [ ] Milestone numbering is global and consecutive across phase files.